Update on 5th Street Bridge Concrete Pour
January 24, 2022
Crews encountered some challenges with the materials last night. The concrete mix needs to meet very specific criteria and on-site tests showed it wasn’t meeting requirements.
Once the concrete starts flowing the contractor will only have one shot to get it poured and finished, so at around 9:30 pm on Sunday they made the call to cancel the planned pour. Investigations are underway and they will regroup and reschedule.
We are so close to the finish line! We appreciate your patience. Please stay tuned: as soon as we have a new date we will let you know. Thank you.