Description:

The City of Courtenay anticipates that the following procurement will be released in the near future per the details below. This scope and schedule are tentative and subject to change at the City’s discretion. The scope of work highlights include:

  • Site preparation, excavation, and removals;
  • Supply, fabrication, and erection of new pedestrian/cycling cable-stayed steel bridge over the Courtenay River and approach retaining walls;
  • Construction of trail tie-ins, paving, and civil works at Simms Millennium Park side;
  • Installation of electrical works for bridge lighting, cyclist counter, and miscellaneous components;
  • Intersection upgrades at 6th Street and Anderton Ave and along 6th Street, including traffic management while working in the roadways;
  • Landscaping across the project site, including plantings and hydroseeding;
  • Supply and installation of security screening beneath bridge back spans; and
  • Supply and installation of critter passage at east approach.

Further information can be found on BC Bid: https://bcbid.gov.bc.ca/page.aspx/en/bpm/process_manage_extranet/205468

Contact Information:

Graham Peterson, Procurement Specialist

purchasing@courtenay.ca

Documents:

No additional documents available for this post.