1st Street Lift Station Upgrades
Start: Spring 2024
End: Winter 2024
Last Updated: January 6, 2025
Hazelwood Construction Services Inc., working on behalf of the City of Courtenay, will be replacing the existing lift station located inside a concrete block building at 1201 – 1st Street, adjacent to the entrance to Puntledge Park, and upgrading the sanitary sewer system. These upgrades are essential to improve the overall service of the local sewer system, mitigate operational risk, and reduce ongoing maintenance costs.
Traffic Notices/Project Updates:
- There are no current notices/advisories for this project.
The project includes:
- Installation of a new lift station, including a 7.0m deep wet well, pumps, an above-ground valve chamber, a power and controls kiosk, and site fencing to enclose the new lift station.
- Installation of approximately 450m length of gravity sanitary sewer main on 1st Street.
- Installation of approximately 250m length of sanitary sewer force main between 1st Street and Pidcock Avenue through an existing City owned Right of Way.
Construction Began Spring 2024